P/A
2018.0523.9894 SAC/DBI (Plans) Approved 9/3/20
("9894")
|
P/A
2021.1112.2309 SAC/DBI (Plans) Approved 1/6/22
("2309")
|
P/A
2021.1112.2309 SAC/DBI (Details) Approved 1/6/22
("2309")
|
10/25/21
Status Quo
12/1/21 Reinforcing of second
(final) sequence of not concreted underpinning pits
South of Line 4 (9894)
|
12/1/21
Begin excavation for foundations North
of Line 4 (9894/2309)
|
12/13/21 Reinforcing of second (final) sequence of underpinning pits South of Line 4 (9894) |
` |
12/14/21 Concreting of second (final) sequence of underpinning pits South of Line 4 (9894) |
1/12/22
Forming over neat-cast grade beams
(partial) South of Line 4
(9894)
Superintendent (Reed DeVost)
Foreman (Alfredo Palma)
|
1/13/22 Concreting forms over to be cast-neat grade beams (partial) South of Line 4 (9894) |
1/20/22 Continued grade beam construction South of Line 4 (9894) |
1/24/22 Continued construction South of Line 4 (9894) 1/27/22 Foundation additions along Line 4 (9894) |
2/3/22
Continued foundation rebuilding along
Line 4
(9894)
2/3/22 Concreting grade beams
South of and along Line 4 (9894)
|
2/3/22 Concreting grade beams South of Line 4 and formed foundation modifications along Line 4 (9894) |
2/3/22 No work North of Line 4 (2309) while concreting grade beams South of and along Line 4 (9894) |
2/10/22 Set up with conveyor for excavation for foundations North of Line 4 (2309) |
2/14/22
Foundation construction South of Line 4 (9894) &
readying for excavation North of Line 4 (2309)
|
2/17/22 Foundation construction South of Line 4 (9894) & excavation in collapsing old fill North of Line 4 to Line 1 (2309) |
2/21/22
Foundation construction readying for
concrete in garage and underslab area South of Line 4
(9894)
|
2/22/22
am Foundation construction
readying for concrete South of Line 4 (9894)
& Excavation/shoring of shallow fill North
of Line 4 (2309)
|
2/22/22
pm Near final concreting
grade beams between garage and Line 4, South of Line 4
& readying for shotcreting replacement of SW
foundation wall (9894)
|
2/22/22
pm Pause in excavation of fill
above bedrock under former deck and between existing
[2021] drilled shafts North of Line 4 (2309)
|
2/25/22 Foundation SW of Line 4 (9894) & excavation/shoring of fill above bedrock under former deck and deep between drilled shafts North of Line 4 to Line 1 (2309) |
3/4/22 Foundation demolition SW of Line 5 & 4 (9894) |
3/4/22 Shoring of fill above bedrock under former deck and deep excavations to weathered bedrock between drilled shafts North of Line 4 to Line 1 (2309) |
3/7/22 Foundation wall demolition SW of Lines 5 & 4 (9894) |
3/7/22 Shoring of fill above bedrock under former deck and deep excavations to weathered bedrock [logged] between drilled shafts North of Line 4 to Line 1 (2309) |
3/9/22 Foundation wall demolition SW of Lines 5 & 4 (9894) |
3/14/22 Tieback retaining foundation construction N of Line 4 in abeyance (2309) & Shotcrete panel and foundation wall demolition SW of Lines 5 & 4 (9894) |
3/16/22
Foundation demolition SW of Lines 5
& 4 (9894) & Excavation/shoring for segments
of tieback retaining wall North of Line 4 (2309).
|
3/18/22 Foundation wall shotcrete preparation SW of Lines 5 & 4 (9894) & Excavation/shoring for staging segments of tieback retaining wall North of Line 4 (2309). |
3/22/22 Foundation wall shotcrete preparation SW of Lines 5 & 4 (9894) & Excavation/shoring [construction in abeyance] for segments of tieback retaining wall North of Line 4 (2309). |
3/24/22
Concreting footing in preparation for
foundation wall shotcrete SW of Lines 5 & 4
(9894).
|
3/24/22
Continued excavation for tieback
retaining wall segments to connect existing drilled
shafts N of Line 4 (2309).
|
3/24/22 Shotcreting foundation wall SW of Lines 5 & 4 (9894). |
3/26/22 Shotcrete foundation wall SW of Lines 5 & 4 (9894). |
3/28/22 Bushing and drilling existing drilled shafts for connection of tieback retaining wall segments N of Line 4 (2309). |
3/31/22 Forming, bushing and drilling existing drilled shafts for connection of tieback retaining wall segments N of Line 4 (2309). |
4/1/22 Epoxy grouting reinforcing bars though and doweled into existing drilled shafts to connect tieback retaining wall segments N of Line 4 (2309). |
4/4/22 Shotcrete test panel [Norcal] (9894). |
4/5/22 Splicing reinforcing bars to dowels at corners and to bars through existing drilled shafts to connect segments of tieback retaining wall to drilled shafts N of Line 4 (2309). |
4/7/22 Splicing reinforcing bars to bars through existing drilled shafts and dowels at corners to connect segments of tieback retaining wall to drilled shafts N of Line 4 (2309). |
4/11/22 Reinforcing tieback retaining wall segments between drilled shafts N of Line 4 (2309). |
` |
4/19/22 Concreting of all tieback retaining wall segments between drilled shafts N of Line 4 (2309). |
4/22/22 Foundation and lateral support (9894/2309) |
4/22/22
Wall forming (9894)
|
5/3/22
Tieback wall (upper) reinforcing for shotcrete
(9894)
Interior iron work (9894)
Ir
|
5/5/22 Tieback wall (upper) shotcreteing (9894) |